From 27 November 2026, the Northern Territory’s pipeline licensing framework expands to cover hydrogen and carbon dioxide. The reforms also make it possible to expand a pipeline licence area after construction and introduce changes to route marking, pipeline management plans and emergency land access. legislation.nt.gov.au
For APGA members who own or operate pipelines in the Territory, the most immediate action is to check route marking against the current Australian Standard AS 2885.1. Operators have a 12-month transition period to bring route marking into line with the standard.
What changes for pipeline projects?
The Energy Pipelines Act 1981 becomes the Pipelines Act 1981. Alongside energy-producing hydrocarbons, the Act provides for licensing onshore pipelines that carry carbon dioxide, hydrogen, and compounds, precursors or carriers used to transmit hydrogen. This gives members developing hydrogen and carbon dioxide transport projects in the Territory a clear pathway to apply for a pipeline licence.
For existing pipelines, licensees can apply to extend their licence area after construction is complete. This could support projects such as adding a parallel section of pipe, known as a loop, to increase storage capacity. Where a proposed variation would bring new land into the licence area, the licensee must consult those affected, and the Minister must consider their submissions.
A fit and proper person test also applies when the Minister grants a pipeline permit or grants, renews or transfers a pipeline licence. Applications lodged before commencement will continue to be assessed under the previous rules, and existing consents remain in effect.
What should operators and contractors review?
Pipeline management plans. Plans must be prepared in line with any guidelines issued under the Act. Modification and decommissioning work requires an approved scope of validation, whether the work is covered by a new plan or a variation to an existing one. If a licensee proposes work outside an accepted plan, it can apply for an exemption after the work has been considered and approved through the plan’s change management process.
Emergency land access. Licensees, their employees and contractors have a statutory right to enter land to comply with a relevant direction or respond to a pipeline emergency. This can include protecting public safety, repairing a pipeline or addressing environmental damage following an incident. The licensee must notify the landowner or occupier and the regulator. Members should check that their emergency procedures identify who will give notice and record the reason for entry, the work undertaken or proposed, and a contact person.
Compliance and enforcement. Inspectors have clearer powers to enter certain land and premises, gather evidence, test equipment and issue directions. The regulator can also issue compliance directions and, in specified circumstances, stop-work notices.
What changes in NT coastal waters?
For members operating under the Territory’s submerged lands legislation, activities will come under the general NT work health and safety framework administered by NT WorkSafe. The offshore pipeline licensing framework also expands to cover hydrogen, hydrogen carriers and greenhouse gas substances.
Previously accepted pipeline management plans and environment plans will continue in effect. A separate two-year transition applies to the new environmental regulations for pipelines that did not have an accepted environment plan immediately before commencement.
The NT Department of Mining and Energy can assist with specific questions. Direct permit and licensing enquiries to the Energy Titles Unit and questions about pipeline operations and approvals to the Petroleum Operations Unit.
View the amending regulations on the NT Legislation website.